The Bowling Green.
The Members are now responsible for the maintenance of the bowling green. This page will be a diary of the maintenance carried out on the green and surrounds throughout the year. Any comments will be welcome since the views of members are important and valued.
A group of volunteers has come forward and these have been divided into four sub-groups. As the season gets under way these sub-groups will be responsible for green maintenance for a week in rotation so that on average a sub-group will be on call for one week in each calendar month. It is anticipated that the duties will be mainly grass cutting and green watering as the season progresses.
The sub-groups are as follows.
| Group A. | Group B. | Group C. | Group D. |
| Brian Holt Greg Deakin |
Goff Hawkins David Slater John Shaw |
Alan Westwood Phil Reader Derek Gallear |
Wal Underwood Denis Kirkland |
The co-ordinator, in the absence of a volunteer, is David Slater so any queries or suggestions should be channelled through him. It is hoped a permanent co-ordinator will soon come forward.
Diary of Work.
2012
16th February. Green deep-slitted using sisis machine loaned by Littleton B.C. (Brian Holt, Dave Slater).
18th February. Green deep-slitted across and back. (Greg Deakin, Wally Underwood, Dave Slater).
2011
17th February. Green scarified lightly diagonally. Grass cut lightly. (Phil Reader, David Slater). Retaining blocks inserted. (Brian Holt, Denis Kirkland).
18th February. Retaining blocks inserted. Rear ditchboards re-aligned and screwed into concrete. (Brian Holt, Denis Kirkland).
22nd February. Final retaining blocks inserted. (Brian Holt, Denis Kirkland, Greg Deakin, Wal Underwood).
23rd February.
Fertilizer spread over green using Cricket Club's spreader. This application
helps to kill off moss and kick starts the growth process
of the grass and is a 5 - 0 - 8 mixture.
7th March.
There has been surprisingly little rain so there are still some granules on
the surface but the chemicals have done their job.
Weather permitting the
green will be scarified and cut this week.
8th March.
Green scarified lightly from pavilion and back, cut lightly across and back.
(Phil Reader, Dave Slater).
The next application will be a 16 - 4 - 8 mixture called superstart which will
be applied in early April.
In May/June a summer mixture 15 - 4 - 8 will be applied.
10th March. Corner of green at entrance gate returfed. (Greg Deakin).
13th March. Some rain at last to wash the last of the granules in. Tried, rather unsuccessfully, to get rid of the moss using domestic scarifiers.
15th March. Using a watering can, Caste-off applied to green especially round the edges
where worm casts are most prevalent. (Dave Slater).
Work carried out on concrete walkway around the green. (Brian Holt). Retaining
blocks painted. (Denis Kirkland).
17th March.
Gaps between concrete slabs on walkway round green filled with cement mixture
and made safe. (Brian Holt, Denis Kirkland).
Floor area and frontage of pavilion painted using Ronseal Red Cedar. (Wal
Underwood, Greg Deakin).
21st March Grass cut diagonally. (Phil Reader).
26th March Grass cut diagonally in opposite direction. (Phil Reader, Greg Deakin, Dave Slater).
30th March Blade setting reduced to 6mm and grass cut. (Phil Reader, Greg Deakin, Denis Kirkland).
2nd April Grass cut. (Brian Holt, Denis Kirkland, Phil Reader).
4th April Grass cut diagonally. (Greg Deakin, Brian Holt, Dave Slater). Second batch of fertilizer ordered for Thursday.
8th April Grass cut. (Greg Deakin, Wally Underwood, Denis Kirkland, Brian Holt).
12th April
Dragbrushed and grass cut diagonally at 6mm blade height which is low enough at
present. (Wally Underwood,
Goff Hawkins, Dave Slater).
16th April Dragbrushed and grass cut up and down. (Dave Slater).
19th April Green cut. (Phil Reader, Alan Westwood).
22nd April Green watered thoroughly due to lack of rain. (Phil Reader, Dave Slater, Greg Deakin).
23rd April Dragbrushed and grass cut. (Phil Reader, Dave Slater).
30th April Still no rain and no prospect of rain. Grass cutting has been reduced and we shall have to water after the weekend hockey.
2nd May Green watered. (Brian Holt, Greg Deakin, Dave Slater).
3rd May Grass cut diagonally, gate corner to marigold corner. (Brian Holt, Denis Kirkland).
6th May Green watered. (Brian Holt, Dennis Kirkland, Greg Deakin).
7th May Rain at last which means we may be able to apply the fertiliser this week, fingers crossed.
9th May Grass cut diagonally from bench corner to car park corner. (David Slater).
14th May Dragbrushed and grass cut across in front of pavilion. Fertilizer applied. (Wal Underwood, Dave Slater).
17th May Grass cut diagonally from gate to marigold corner. (Phil Reader).
19th May Grass cut up and down to pavilion. (Phil Reader).
22nd May Grass cut diagonally from bench corner to car park corner. (Dave Slater). Any rain up there ??
23rd May Green watered and then some much needed rain.
25th May Dragbrushed and grass cut across in front of pavilion. (Greg Deakin, Dave Slater).
28th May Applied phostrogen feed to stressed areas using watering can. (David Slater).
29th May Grass cut from gate corner to marigold corner. (Brian Holt, Greg Deakin, Denis Kirkland).
31st May Dragbrushed and grass cut up and down from pavilion. (David Slater).
2nd June Dragbrushed and grass cut across and back in front of pavilion. (David Slater).
4th June Green cut up and down from pavilion. (David Slater).
6th June Green cut across and back. (Phil Reader).
7th June Green cut from pavilion end and back. (Phil Reader)
9th June Green cut from gate to marigold corner. (Phil Reader).
11th June Green cut from bench to car park corner. (Phil Reader).
14th June Green cut from pavilion end and back. (Denis Kirkland and Wally Underwood).
16th June Dragbrushed and grass cut across and back in front of pavilion. Blade lowered. (Wally Underwood, Dave Slater)
17th June Green spiked using garden forks and the Holt machine. (Alan Westwood, Brian Holt and Mary Camp).
19th June Dragbrushed and cut from bench corner to car park corner. (Greg Deakin, Brian Holt).
21st June Green cut. (Brian Holt, Greg Deakin).
23rd June Green cut diagonally. (Greg Deakin, Brian Holt).
26th June Green scarified up and down from pavilion and cut across and back. (Dave Slater)
28th June Green cut up and down from pavilion. (Dave Slater).
30th June Green cut across and back. (Dave Slater).
4th July Green cut up and down from pavilion. (Phil Reader).
6th July Grass cut. (Phil Reader).
9th July Green cut across and back. (Phil Reader)
10th July Wetting agent applied to stressed areas. (Dave Slater).
11th July Grass cut diagonally. (Denis Kirkland, Wally Underwood).
14th July Grass cut. (Greg Deakin, Wally Underwood).
16th July Grass cut up and down from pavilion. (Brian Holt, Denis Kirkland, Dave Slater).
19th July Grass cut diagonally. (Brian Holt, Greg Deakin).
23rd July Green
scarified from pavilion up and down. Carbendazin applied to eradicate worm casts
along in front of pavilion and along start side
of green. Wetting agent applied to the worst stress areas to stimulate growth.
(Dave Slater)
26th July Green cut across and back. Very little grass growth due to dry spell. (Dave Slater).
27th July Green watered. (Brian Holt, Dave Slater).
29th July Grass cut up and down from pavilion. (Dave Slater).
1st Aug. Green watered thoroughly. (Dave Slater). Outside water tap fitted. (Brian Holt, Wally Underwood).
2nd Aug Grass cut. (Phil Reader).
4th Aug. Grass cut diagonally. (Phil Reader).
6th Aug. Green scarified and grass cut up and down from pavilion. (Dave Slater).
10th Aug. Green spiked using garden forks and the Holt machines
11th Aug Green spiked using spike cassette on mower. (Phil Reader, Brian Holt).
14th Aug Green cut. (Greg Deakin, Brian Holt).
15th Aug Green watered thoroughly. (Dave Slater).
16th Aug Verti-cut
cassette used up and down followed by normal cut across and back. Weed killer
applied to clover. (Phil Reader, Greg Deakin,
Dave Slater).
19th Aug. Grass cut up and down. (Greg Deakin, Wally Underwood).
21st Aug Attempted to water green but unable to do so because water was turned off.
22nd Aug Green watered. (Greg Deakin, Wally Underwood, Phil Reader, Dave Slater).
24th Aug. Green cut using verti-cutter (eleven bin loads of grass) then rain prevented normal cutting. (Phil Reader).
25th Aug Meeting of volunteers held. Grass cut when green dried out after good rainfall. (Dave Slater)
26th Aug Arranged visit by David Bates next Thursday at 9.30 a.m.. Green spiked using sorrel roller (Phil Reader).
3rd Sept Caste-off applied to perimeter of green to prevent worm casts.
5th Sept Green cut across and back. (Denis Kirkland, Wally Underwood).
Sept. Stressed areas treated with top soil and grass seed. (Phil Reader, Greg Deakin).
1st Oct. Green
hollow tined for the first time ever. Plugs removed as much as possible. (Large
group of volunteers).
Later in the day green watered for two hours and more plugs removed. (Alan
Westwood, Dave Slater).
2nd Oct. Green hollow tined again after watering yesterday, more plugs removed. (Large group again).
3rd Oct Green watered again and plugs removed. (Alan Westwood, Dave Slater).
4th Oct. Took delivery
of 160 bags of top dressing and placed at intervals round the green. Received
also 3 * 25 kg. bags of winter granular
fertiliser. (Dave Slater, Brian Holt, Alan Westwood and Neville Harrison pitched
in !).
8th Oct. Winter feed
applied to green (5-3-20+1% Iron mix, £27 per 25 Kg Bag). More hollow tining
carried out using the Chalenor tool. (Greg
Deakin,
Dave Slater).
12th Oct Four tonnes of top dressing applied (160 bags). (Large group of volunteers).
20th Oct Top dressing applied round edges of green. (Dave Slater).
21st Oct Remainder of top dressing applied. Grass cut with raised blade. (Phil Reader, Dave Slater).
2nd Nov Grass cut across and back. (Phil Reader).
23rd Nov Dragbrushed green up and down from pavilion. (Dave Slater).
24th Nov Dragbrushed green across and back, grass cut up and down. (Dave Slater).
25th Nov Green deep slitted using machine borrowed from Littleton B. C. (Brian Holt, Greg Deakin, Wal Underwood, Dave Slater).